Carrier Mini-Split: Voltage checks at start-up
Voltage checks at start-up on a Carrier mini-split: Check voltages at the outdoor disconnect, outdoor terminal block and indoor unit before running the system.
Applies to: Single zone ductless start-up
How to fix voltage checks at start-up: step by step
- Measure 1(L1) to GND and 2(L2) to GND at the outdoor unit disconnect.
- Measure the same points at the outdoor unit terminal block.
- Measure 1(L1) to 2(L2) at the outdoor terminal block.
- Measure 1(L1) to GND, 2(L2) to GND, 1(L1) to 2(L2), and 2(L2) to 3(S) at the indoor unit.
- Record readings on the Voltage Check section of the start-up checklist.
If the unit shows an error code, look it up: Carrier Mini-Split codes
Source: Carrier D5FCFA installation manual, p. 23. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.