Weil-McLain Boiler: Sidewall vent termination location and clearances
Sidewall vent termination location and clearances on a Weil-McLain boiler: Choose a termination spot that stays clear of debris, snow and other terminations.
Applies to: SVF 500/600 Category IV direct vent, sidewall termination, single or multiple boilers
How to fix sidewall vent termination location and clearances: step by step
- Pick a location where foreign objects and leaf or sediment buildup are unlikely.
- Keep the termination above grade and snow line, and keep vent and air openings clear of snow.
- Place the boiler so the vent can be routed from the boiler vent connection to the chosen sidewall spot without exceeding the Figure 22 maximum length (p. 36).
- Terminate all vent and air inlet pipes at the same height.
- Keep at least 12 in between the edge of a vent opening and an adjacent termination (Figure 48, p. 58).
- For other appliances, keep at least the clearance shown. Their installation must also follow this manual.
- In the US, meet the clearances in Figure 48 and Figure 36 (p. 49).
- In Canada, meet CAN/CSA B149.1 or B149.2 and use a ULC S636-compliant vent kit.
- The air inlet is part of a direct vent connection and is not treated as a forced air intake for spacing from adjacent boiler vents.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: Weil-McLain SVF 500/600 Series 1 boiler manual, p. 58. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.