Weil-McLain Boiler: Multiple boiler terminations and vent/air clearances
Multiple boiler terminations and vent/air clearances on a Weil-McLain boiler: Spacing rules when more than one SlimFit boiler terminates on the same wall or roof.
Applies to: SF-550 and SF-750 with multiple boilers
Common causes of multiple boiler terminations and vent/air clearances
- Vent outlets and air inlets at different heights
- Vent pipe of one boiler too close to the air inlet of the next
How to fix multiple boiler terminations and vent/air clearances: step by step
- Terminate every vent/air connection as described in this manual for individual vents.
- Set all vent pipes and air inlets at the same height.
- Place wall penetrations for at least 12 in between a vent pipe and the adjacent air inlet elbow (US installations).
- For Canadian installations, follow the clearances in CSA B149.1 or B149.2.
- Treat the direct vent air inlet as part of a direct vent connection, not as a forced air intake for spacing from adjacent vents.
- Space terminations for good installation practice and required maintenance access.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: SlimFit series 3 commercial gas-fired water boiler manual, p. 33 and p. 40. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.