Weil-McLain Boiler: WMZV zone valve zone controller plus DHW (DHW piped to boiler)
WMZV zone valve zone controller plus DHW (DHW piped to boiler) on a Weil-McLain boiler: Input 2 takes the space heating call from the zone controller. The system circulator on Output 2 runs on any space heating call. DHW is on Input 1 at Priority 1.
Applies to: SVF Series 1 with WMZV zone valve controller
How to fix wmzv zone valve zone controller plus dhw (dhw piped to boiler): step by step
- Wire the zone controller call (X-X) to Input 2 and keep Input 2 on Priority 2.
- Set Priority 2 for the space heating system type.
- Wire the system circulator to Output 2.
- Wire the DHW aquastat to Input 1, assign Input 1 to Priority 1, and wire the DHW circulator to Output 1.
- Use the factory DHW settings or change them as needed.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: SVF 1500-3000 Series 1 boiler manual, p. 67. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.