Weil-McLain Boiler: Vertical concentric termination: roof penetration
Vertical concentric termination: roof penetration on a Weil-McLain boiler: Prepare the roof opening and thimble before running the termination through it. Follow local codes for isolating vent pipe through floors, ceilings and roofs.
Applies to: 3 in and 4 in vertical concentric termination
How to fix vertical concentric termination: roof penetration: step by step
- For a 3 in termination, cut a 5 in diameter hole to clear the 4-1/2 in outside diameter.
- For a 4 in termination, cut a 6-1/2 in diameter hole to clear the 6 in outside diameter.
- Insert a galvanized metal thimble in the vent pipe hole.
- Install flashing and sealing boots sized for the concentric termination outside diameter.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: Ultra Series 4 boiler manual, p. 76. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.