Weil-McLain Boiler: Install vent and air pipe from the boiler outward
Install vent and air pipe from the boiler outward on a Weil-McLain boiler: Build the vent and air system working from the boiler toward the termination. Do not exceed the length limits for either the air or vent pipe.
Applies to: ECO Tec Series 3 vent and air piping
How to fix install vent and air pipe from the boiler outward: step by step
- Follow the instructions for the termination type and the vent pipe manufacturer before starting.
- Attach pipes at the boiler: 3" PVC for air inlet; 3" PVC, CPVC, stainless or polypropylene for vent (use transitions if needed).
- Cut pipe to length.
- Dry-fit the entire vent or air run before cementing any joint.
- Keep at least 3/16 in. clearance between vent pipe and any combustible wall or material.
- Seal wall and floor penetrations per local code.
- Use sweep elbows only for all vent and air piping.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: ECO Tec series 3 boiler manual, p. 32. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.