Weil-McLain Boiler: Example D high mass boiler with isolation heat exchanger
Example D high mass boiler with isolation heat exchanger on a Weil-McLain boiler: Condensing boilers run during low-load periods such as spring and fall. A high-mass boiler is added for high-load periods. The control sequences the high-mass boiler in when it is needed, through the additional heat demand input.
Applies to: Example D multi-boiler with isolation heat exchanger and high-mass boiler
How to fix example d high mass boiler with isolation heat exchanger: step by step
- Pipe the isolation heat exchanger and high-mass boiler as shown in Figure 15.
- Install unions where recommended, drain valves at 3/4 inch NPT or larger, and the boiler T&P gauge.
- Provide a strainer on each boiler return line where recommended.
- Place immersion sensors on the supply and return at least 6 pipe diameters, and no more than 3 feet, from the boiler connection tees.
- Confirm the control sequences the high-mass boiler when needed.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: Series 2 Condensing Gas Boiler Advanced Manual, p. 31. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.