Weil-McLain Boiler: Assemble the pedestal floor stand
Assemble the pedestal floor stand on a Weil-McLain boiler: Assemble the floor stand kit 383-800-245 and attach it to the boiler cabinet before setting the boiler upright.
Applies to: Pedestal floor stand installations
How to fix assemble the pedestal floor stand: step by step
- Set the boiler on its back, removing it from the styrofoam base.
- Lay the front section (A) flat. Install cross-supports (B) with the bent flange facing front, using eight 1/4 inch machine screws, nuts and washers. Hand tighten.
- Set the back section (F) on its back. Position the front section over it and fasten with eight 3/8 inch screws, nuts and washers. Use the holes for the specific model (80/110/150 or 199). Hand tighten only at this stage.
- Install the leveling legs into the rivets on the bottom of the stand and screw them all the way in. Do not overtighten.
- Hand install four 5/16 inch studs into the rivet nuts on the bottom of the boiler cabinet, with the short threaded end into the cabinet.
- Position the stand over the studs and against the cabinet bottom. Align the sides and curved corners with the cabinet and door. Secure with four 5/16 inch nuts without overtightening.
- Install the condensate trap assembly (see page 63) before lifting.
- Fully tighten all nuts, then lift the boiler upright with help.
- Level the boiler by turning the leveling legs with a flat head screwdriver.
- Install the floor stand door on the front section.
If the unit shows an error code, look it up: Weil-McLain Boiler codes
Source: ECO Tec Series 3 boiler manual, p. 15-16. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.