Viessmann Boiler: Verify gas input by clocking the gas meter
Verify gas input by clocking the gas meter on a Viessmann boiler: Time how long the boiler takes to burn a set amount of gas and compare with the nameplate input. Other gas appliances on the meter must be off during the test.
Applies to: Vitocrossal 300 CU3A 26 to 199 (low altitude)
How to fix verify gas input by clocking the gas meter: step by step
- Turn off all other gas appliances served by the meter.
- Time how many seconds the boiler takes to use 10 ft3 of gas.
- Confirm the heating value of the gas with the gas utility first.
- Calculate input: (3600 x 10) divided by seconds gives ft3 per hour; multiply by heating value (Btu/ft3) to get Btu/h.
- Example: a 199 model at 181 seconds per 10 ft3 with 1000 Btu/ft3 gives about 199,000 Btu/h, which is correct.
- An input 5% under the rating is acceptable. Do not overfire the boiler.
- Metric or low altitude formulas: INPUT = (3600 / t) x 1000 with t in seconds per 1 ft3; or INPUT = (3600 x 0.01 x 1000 x 35.31) / T with T in seconds per 0.01 m3 of natural gas. These apply to low altitude only.
If the unit shows an error code, look it up: Viessmann Boiler codes
Models
CU3I 2ZC2ZP.01CU3I 3HC/Z3ZP.01CU3X 1ZC1ZP.01Vitocrossal 300 CU3A 26Vitocrossal 300 CU3A 35Vitocrossal 300 CU3A 45Vitocrossal 300 CU3A 57Vitocrossal 300 CU3A 94Vitocrossal 300 CU3A 125Vitocrossal 300 CU3A 160Vitocrossal 300 CU3A 199
Source: Vitocrossal 300 CU3A 26 to 199 Service Instructions, p. 27. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.