Viessmann Boiler: Setting a central heating time program
Setting a central heating time program on a Viessmann boiler: Time phases define when rooms heat to standard temperature. Between phases the rooms run at the reduced temperature. Up to 4 phases per day are possible. Each phase has a start and end point, shown as a white bar on the time chart. Example: Mon-Fri with phase 1 at 05:00 to 08:30 h and phase 2 at 16:30 to 23:00 h.
Applies to: Central heating heating circuits
How to fix setting a central heating time program: step by step
- Open the extended menu.
- Select Heating, then the required heating circuit.
- Select Heating time program.
- Select the part of the week or a single day.
- Select time phase 1 to 4.
- Set the start and end points for the phase.
- Press the exit button to leave the menu.
If the unit shows an error code, look it up: Viessmann Boiler codes
Models
CU3I 2ZC2ZP.01CU3I 3HC/Z3ZP.01CU3X 1ZC1ZP.01Vitocrossal 300 CU3A 26Vitocrossal 300 CU3A 35Vitocrossal 300 CU3A 45Vitocrossal 300 CU3A 57Vitocrossal 300 CU3A 94Vitocrossal 300 CU3A 125Vitocrossal 300 CU3A 160Vitocrossal 300 CU3A 199
Source: Viessmann Vitocrossal 300 CU3A operating instructions, p. 18. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.