Viessmann Boiler: Hydrostatic pressure test of the boiler before startup
Hydrostatic pressure test of the boiler before startup on a Viessmann boiler: The boiler must be leak tested before piping or power is connected. Test at no more than 1.5 times the maximum operating pressure. Do not exceed the listed pressure or temperature limits, or the warranty is void.
Applies to: Vitorond 100 VR1 40 to 63 and 161 to 245 oil-fired boilers
Common causes of hydrostatic pressure test of the boiler before startup
- Pressure above the listed limits can damage the boiler
- Leaks at pipe joints, safety devices or the boiler base
How to fix hydrostatic pressure test of the boiler before startup: step by step
- Install safety devices, then fit a temporary cap on the 3/4 in. nipple used for the relief valve.
- Cap the supply and return connections.
- Connect a 1/2 in. garden hose to the boiler drain valve and fill slowly until the gauge reads 68 psi (4.65 bar).
- Hold pressure for 15 minutes and stay with the boiler during the test.
- Check all pipe joints, safety devices (safety header if fitted) and the boiler base with a flashlight for leaks.
- Open the drain valve slowly to release pressure, then remove the caps.
- Install the pressure relief valve in place of the 3/4 in. cap before startup.
If the unit shows an error code, look it up: Viessmann Boiler codes
Source: Vitorond 100 VR1 installation and service manual, p. 25. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.