Viessmann Boiler: Boiler pressure test before connecting piping and power
Boiler pressure test before connecting piping and power on a Viessmann boiler: Leak and hydrostatic test on the installed boiler with supply and return headers in place. The boiler must pass before it is connected to piping or power.
Applies to: Installed boiler before start-up
How to fix boiler pressure test before connecting piping and power: step by step
- Install supply and return headers with gauge, thermometer, air vent, low water cut-off, drain valve and bypass pump. Pipe to the isolation valves and close them.
- Install temporary caps on the relief valve and expansion tank nipples.
- Connect a hose to the boiler drain valve and fill slowly until the gauge reads the maximum test pressure.
- Hold pressure for 30 minutes. Do not leave the boiler unattended.
- Inspect all push nipples and pipe joints with a flashlight. Place paper under the block to catch drips from bottom nipples.
- After 30 minutes, open the drain valve slowly to release pressure, remove the caps and install the relief valve and expansion tank right away.
If the unit shows an error code, look it up: Viessmann Boiler codes
Source: Vitorond 200, VD2A Series Installation, p. 24. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.