Commissioning: Heat Pump tips (part 2 of 4)

Updated · by Aurora Star Tech Inc.

Short, practical technician tips on commissioning for heat pump. Check each one against the manual for your exact model before acting.

Selecting indoor unit combinations and system size

Carrier · D5CMHA system selection

If the system will run at maximum load for most of the time, select the next larger system capacity. Use the application tables to confirm the indoor unit combination for the outdoor size.

  1. Estimate how often the load stays near maximum.
  2. If it runs near maximum most of the time, select the next larger outdoor size.
  3. Confirm the indoor combination in the application tables.

Separate power and control wiring

Carrier · D5CURA field wiring

Control signal cable must be run apart from power wiring to avoid interference. Metal conduit or shielded cable is recommended.

  1. Run control signal cable separately from power wiring.
  2. Keep at least 12 in (300 mm) between control wiring and power wiring.
  3. Do not run power and control wiring in the same conduit.
  4. Size all wiring per NEC/CEC and local codes, and use different colors for different wires.

Triple evacuation method (when the pump cannot reach 500 micron)

Carrier · D5CURA evacuation when deep vacuum is not possible

Use only if the vacuum pump cannot pull 500 micron and the system holds no liquid water. Always break vacuum with dry nitrogen.

  1. Attach gauges and evacuate the system to 28 in Hg. Keep the pump running for 15 more minutes.
  2. Close the service valves and shut off the pump.
  3. Connect a nitrogen cylinder with regulator and flow nitrogen until system pressure reads 2 psig.
  4. Close the service valve and let the system stand for 1 hour so the dry nitrogen can absorb moisture.
  5. Repeat the evacuation and nitrogen steps as shown in Fig. 20 until the system is clean and dry.

Run the outdoor commissioning sequence (steps 01 to 17)

Gree · Gree GMV6 Ultra Heat Mini VRF 36-60k (GMV-V..WL/C-T(U))

On a new system or after replacing the outdoor main board, the outdoor display walks through numbered commissioning steps; a step with a fault shows the fault code and resumes once it is cleared.

  1. Start: when the board shows A0, hold SW3 for 5 seconds.
  2. 01 set master unit, 02 allocate addresses, 03 confirm outdoor quantity, 04 confirm indoor quantity (SW3 to confirm).
  3. 05 outdoor drive communication and capacity ratio, 06 outdoor components, 07 indoor components.
  4. 08 compressor preheat (SW3 may be used to confirm 8 hours have passed), 09 refrigerant check, 10 outdoor valve check (U6 shows if the valves are not fully open).
  5. 12 confirm start (AP, then AE), 15 cooling debug (AC) or 16 heating debug (AH), each passing after 50 minutes with no fault.
  6. 17 finished: oF and standby.

Activate frost protection before filling the secondary circuit

Viessmann · Vitocal 100-WA

Frost protection only works when the heat pump is electrically connected, so power must be on first.

  1. Thermally insulate all hydronic lines.
  2. Connect the heat pump electrically and switch on the power supply.
  3. Only then fill the secondary (hydronic) circuit.

Antifreeze and water treatment at fill

Viessmann · Vitocal 100-AW hydronic system

Treat the fill water where minerals or hardness are known to be a problem, and add antifreeze only where freezing can occur.

  1. Check hardness and pH of the fill and top-up water before filling.
  2. If hardness is high or pH is out of range after operation, take corrective treatment.
  3. Keep antifreeze at or below 50% glycol and check the system often when it is filled with antifreeze.
  4. Check that a backflow preventer is in the automatic water feed when a glycol mix is used.
  5. Tell the system operator the system contains glycol and provide the antifreeze Safety Data Sheet (SDS).

Buried refrigerant line limits and tubing check

Viessmann · DLCSRB outdoor units, all sizes

Limits for buried line runs and checks before charging the system.

  1. Do not bury more than 36 in (914 mm) of refrigerant line.
  2. If any line is buried, give it a minimum 6 in (152 mm) vertical rise to the outdoor service valves.
  3. Check that factory tubing has not shifted in shipping.
  4. Check that tubes do not rub each other or sheet metal.
  5. Check that the wire ties on the feeder tubes are secure and tight.

Buried refrigerant pipe limits

Viessmann · DLCURA field piping

Do not bury more than 36 in of refrigerant pipe. If any section is buried, the pipe must rise at least 6 in to the outdoor unit valve connections. Too much buried pipe lets refrigerant migrate and can cause slugging at start-up.

Check factory tubing before final connection

Viessmann · DLCLRC indoor and outdoor units

Factory tubing can shift in shipping and rub. Check it before finishing the install.

  1. Check that factory tubing on both indoor and outdoor units has not shifted.
  2. Make sure no tubes rub against each other or sheet metal.
  3. Check that wire ties on the feeder tubes are secure and tight.

Check water connections for leaks

Viessmann · Vitocal 100-WA

Escaping ground loop water or DHW can cause electric shock risk, so check all water side connections.

  1. Fit new gaskets or seals on every connection that was opened or loosened.
  2. During commissioning and after any maintenance, check all water side connections for leaks.

Closed loop flow and loop temperature

Viessmann · Closed loop systems

Closed loops need a minimum of 3 GPM/ton (11.5 LPM/3.5 kW), based on a loop designed for 32 to 90°F (0 to 32°C). Use higher flow if design temperatures fall outside that range. The loop pump depends on the project loop design; residential systems typically use one pump per unit.

  1. Confirm loop design temperature is within 32-90°F.
  2. Size the loop pump for at least 3 GPM/ton.
  3. Increase flow if loop temperatures fall outside the range.

Closed loop purging and pump mounting

Viessmann · Closed loop systems

Air trapped in the pump will burn it out quickly. Purging needs a minimum velocity in every branch. With several heat pumps on one loop, only one auto purge kit is used.

  1. Mount the ground loop pump vertically so air cannot be trapped in it.
  2. Achieve at least 2 ft/s in every branch of the ground loop while purging.
  3. Use the purge ports for anti-freeze charging.
  4. With two or more heat pumps on one loop, install only one auto purge kit, ideally on the highest unit.
  5. Install check valves and a Y-strainer on each unit.
  6. Keep the auto purge tank ½ to ¾ full at all times.

Communication bus cable between indoor and outdoor units

Viessmann · Indoor and outdoor unit wiring

The indoor and outdoor modules communicate over a bus. Use the specified cable type.

  1. Use two-wire twisted pair, shielded 22 AWG cable between the indoor and outdoor unit.

Condensate drain connections

Viessmann · All D5CSRA systems

Install the drains according to local sanitation codes.

  1. Route the drain lines per local sanitation codes.

Connecting to the control board with PuTTY

Viessmann · Vitocal 100-WA control board

A Windows computer or Android phone/tablet with PuTTY and a USB link is used to view and adjust the control board system run parameters, zone parameters and basic system program.

  1. Install PuTTY on the computer or device.
  2. Open PuTTY and note the COM port the controller uses; check Device Manager under Ports (COM & LPT).
  3. If several COM ports are in use, unplug the controller to see which port disappears, then plug it back in.
  4. Connect the USB cable between the computer and the control board and make sure the controller is powered.
  5. Select Connection Type Serial, enter the COM number and set the speed (baud rate) to 250000.
  6. Click Default Settings under Saved Sessions and press Save so these settings load by default.
  7. Press Open on the Configuration page to start communicating with the controller.

DHW desuperheater piping requirements

Viessmann · DHW tank with desuperheater

Use isolation valves and two drain valves so the pump can be serviced without draining the tank. Use a horizontal swing check valve to stop the tank overheating. Copper must match the unit fittings; if 1 in. (25 mm) copper is used, reduce it as close to the tank as possible. Use metal fittings within 12 in. (300 mm) of the desuperheater tee. With a Marathon plastic tank use mechanical fittings at the tank only, and never use plastic fittings between the tank and the unit. Follow the tank installation instructions.

  1. Install isolation valves and two drain valves (tank draining and purging).
  2. Install a horizontal swing check valve.
  3. Use metal fittings within 12 in. (300 mm) of the desuperheater tee.
  4. Reduce 1 in. copper to match the unit as close to the tank as possible.
  5. Upsize long pipe runs if pressure drop is too high.

DHW piping sizing to the indoor unit

Viessmann · Indoor unit DHW connections

DHW piping must not restrict flow, so the internal pump has enough head to push water through the heat exchanger.

  1. Make the DHW supply and return piping between the indoor unit DHW connections and the DHW tank at least the same size as the indoor unit outlets.
  2. With a non-Viessmann tank, calculate the tank coil pressure drop against the indoor unit pump residual head to confirm adequate flow.
  3. Be aware that undersized DHW piping can cause inadequate DHW supply.

DHW tank and DHW piping requirements

Viessmann · Vitocal 100-AW AM2V domestic hot water

A non-Viessmann DHW tank requires the installer to verify the tank temperature sensor with the tank maker. A tempering valve is strongly recommended in the DHW supply line. DHW piping must be at least the size of the Vitocal DHW connections so the integral pump has enough residual head.

  1. For a non-Viessmann tank, verify the DHW tank temperature sensor operation with the tank manufacturer.
  2. Install a temperature tempering valve in the DHW supply line.
  3. Size DHW supply and return piping to at least the Vitocal DHW outlet size.
  4. For non-Viessmann tanks, calculate the tank coil pressure drop against the integral pump residual head.

Duct design and install notes

Viessmann · Ducted installs

Design ducts per ACCA Manual D or local code and keep them inside conditioned space. Attic duct should be low profile, laid on the joists and covered with 6-8 in. (150-200 mm) of insulation. Line the first 6 ft of supply and return with acoustic insulation and use flex duct for the first 6 ft from the grille. Do not undersize the return. Make turns smooth. Do not let screws or drilling reach the air coil.

  1. Design per ACCA Manual D or local code.
  2. Keep ducts inside conditioned space where possible.
  3. Insulate attic ducts with 6-8 in. (150-200 mm) of insulation.
  4. Line the first 6 ft of supply and return with acoustic insulation.
  5. Size the return to avoid pulsation and poor performance.
  6. Keep screws and drilling clear of the air coil.

Factory refrigerant charge and line length

Viessmann · Outdoor unit sizes 18K to 60K

The factory charge in the outdoor unit covers up to 25 ft (8 m) of line length.

  1. For refrigerant lines longer than 25 ft (8 m), add refrigerant up to the allowable length.

Filter drier replacement rule

Viessmann · DLCURA heat pump models

Replace the filter drier any time the refrigeration system is exposed to air. Use only factory liquid-line driers rated below 600 psig. Do not install a suction-line drier in the liquid line.

First power-up language and outdoor unit type

Viessmann · Vitocal 100-AW AM2V indoor unit first start-up

At first power-up the indoor unit asks for the operating language and the connected outdoor unit model. Choose the model that matches the outdoor unit: 020028, 034043 or 051078.

  1. Scroll with the navigation dial to the language and press the dial to select it.
  2. Scroll to the connected outdoor unit type and press the dial to accept it.

Flush the heating system before connecting

Viessmann · Vitocal 100-WA

Flush the heating system thoroughly, especially when adding the heat pump to an existing system.

  1. Flush the whole system before making the heat pump connections.
  2. Use isolation valves so system components can be isolated.

Freeze protection and power failure precautions

Viessmann · Vitocal 100-AW AM2V outdoor unit

Do not switch the unit off when outdoor air is below freezing, because leaving it powered protects the outdoor unit condenser. If power failure is a risk, isolate the heat pump heating circuit from the hydronic module with an additional exchanger and fill that circuit with antifreeze.

  1. Keep the outdoor unit powered when outdoor air is below freezing.
  2. Where power failure is a risk, add an additional exchanger to isolate the heat pump circuit.
  3. Fill the heat pump heating circuit with antifreeze in that case.

Freeze protection tab

Viessmann · Liquid to refrigerant heat exchanger

The ANTIFREEZE tab sets the freeze set point. Breaking it off is permanent and is only allowed on closed loops that have adequate antifreeze.

  1. On closed loops with adequate antifreeze, break off the ANTIFREEZE tab with needle nose pliers if a 20°F (-7°C) set point is wanted.
  2. On open loops, leave the tab in place to keep the 38°F (3°C) set point.
  3. Do not remove the tab on open loops or on closed loops with minimal freeze protection, as this voids the warranty.

Ground loop and DHW connection points

Viessmann · Vitocal 100-WA

Port legend for the water and air connections on the unit. A and B are the ground loop return and supply. C is the condensate line. D is return air and G is supply air. E is the DHW supply to the tank and F is the DHW tank return to the desuperheater. H is an optional field-supplied double O-ring flow center.

Heating water piping practice and pressure limit

Viessmann · Indoor unit heating water and DHW connections

Support all piping with hangers and never let the indoor unit carry the pipe weight. Use two wrenches on fittings so the connector is not twisted. The maximum allowable working pressure is 30 psig (2 bar); exceeding it or the listed temperatures damages the unit and voids the warranty.

  1. Flush the heating system thoroughly, especially before connecting to an existing system.
  2. Install isolation valves so system components can be isolated.
  3. Use approved pipe sealant or Teflon tape on the fittings.
  4. Hold the connector with one wrench and tighten the fitting with a second wrench.
  5. If no DHW tank is connected, cap the DHW tank supply connection.
  6. Keep 2 in. (50 mm) from uninsulated hot water pipes to combustible parts, unless the pipe has suitable insulation.
  7. Install a temperature gauge (field supplied) in the supply piping near the heat pump.

Hydronic installation requirements

Viessmann · Vitocal 100-AW AM2V hydronic system

The hydronic side must follow applicable standards and be sized for adequate flow. Flexible piping is needed to limit vibration. Heating medium piping must be insulated. A solids separator at the unit inlet is required for warranty.

  1. Size the piping between outdoor and indoor units for adequate flow (see technical data table).
  2. Connect the heat pump to the system with flexible piping.
  3. Insulate all heating medium pipes and connections.
  4. Install a solids separator at the unit inlet.
  5. Keep the minimum heating medium pressure at 8 PSI (0.5 bar).
  6. Pipe so the indoor unit can run the heating circuit without the outdoor unit.

Indoor to outdoor connection polarity

Viessmann · DLCLRC sizes 36K-58K

The indoor to outdoor connections are polarity sensitive and a wrong connection will generate a fault code. Do not use thermostat wire for any link between indoor and outdoor units. Use a 2-core shielded wire for the communication link. Use the connection diagram exactly as drawn.

  1. Connect the power and communication wires between outdoor and indoor units as shown in the connection diagram.
  2. Use shielded 2-core communication wire, not thermostat wire.
  3. Check polarity before power-up.

Indoor to outdoor unit connection polarity

Viessmann · DLFSHCH indoor and outdoor unit wiring

Do not run thermostat wire between the indoor and outdoor units. The connections are polarity sensitive, and a wrong connection will cause a fault code. All indoor-outdoor connections must match figures 1 and 2 of the manual.

  1. Do not use thermostat wire between the units.
  2. Wire the indoor and outdoor units exactly as shown in the 115 V or 208/230 V connection diagram.
  3. Confirm polarity on every communication connection before power-up.
Safety: Gas, electrical and refrigerant work must be done by a licensed technician. Turn off power and gas before servicing, never bypass a safety control, and always follow the manufacturer's manual for your exact model.

General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.