Commissioning: Air Handler tips (part 2 of 3)
Short, practical technician tips on commissioning for air handler. Check each one against the manual for your exact model before acting.
Furnace blower failure detection requirement
Carrier · D5FULA crossover evaporator coil with any furnace
When this coil is used with any furnace, the furnace must detect blower failure and verify airflow. Blower feedback must act within one minute to shut off the gas valve.
- Confirm the furnace has blower failure detection and airflow verification.
- Confirm blower feedback shuts off the gas valve within one minute of a blower failure.
Horizontal installation needs a secondary drain pan
Carrier · D5FUAA air handler
Multi-poise unit can be set vertical up, horizontal left or right, or upflow/downflow. Horizontal installs need a secondary drain pan (not supplied) with at least 5 in (127 mm) between the bottom of the air handler and the pan for drainage. Vertical up and horizontal left do not require changing the evaporator direction.
- Confirm the install orientation from the multi-poise drawings.
- For horizontal installs, fit a secondary drain pan not supplied with the unit.
- Keep at least 5 in (127 mm) between the air handler bottom and the secondary pan.
Indoor refrigerant joint leak test
Carrier · Indoor refrigerant joints
Field-made joints indoors must be leak tested with a method sensitive to 5 g/year of refrigerant or better, at a pressure of at least 0.25 times the maximum allowable pressure. No leak may be detected. Detachable joints are not allowed on the indoor side; brazed or welded joints are acceptable.
- Use a leak detector rated 5 g/year or better.
- Test at a pressure of at least 0.25 times maximum allowable pressure.
- Confirm no leak is detected.
- Do not use detachable joints on the indoor side.
Indoor unit power and signal wiring steps
Carrier · D5FUAA indoor unit
Basic wiring order for the base indoor unit. Auxiliary electric heat wiring is covered in the installation manual.
- Turn off the main disconnect and lock it out before opening the unit.
- Strip the signal cable to about 1/2 in (12 mm) and strip the wire ends; crimp fork terminals on each wire.
- Open the front panel and remove the electric control box cover.
- Pass the power and signal cables through the wire outlet.
- Connect each fork terminal to the matching terminal, matching wire colors and labels.
- Tighten each screw and check against the wiring diagram on the control box cover.
- Clamp the cable so it is not loose and carries no strain on the terminals.
- Reattach the electric box cover and make sure it closes fully.
Installation location and drainage
Carrier · D5FULA crossover evaporator coil, sizes 24K - 60K
Install on a firm surface that supports the unit weight. Install drain piping as the manual describes, because poor drainage can cause water damage. Do not install where combustible gas may leak.
Isolate interconnecting tubing from the structure
Carrier · DLFULA evaporator coil with outdoor unit
Isolate the interconnecting tubing from the building structure so vibration and noise do not transmit into the building.
- Isolate the tubing from framing and structure when routing the line set.
Keep high voltage and communication wiring separate
Carrier · Field wiring between indoor and outdoor units
High voltage and communication wire must not run through the same knockout. Keep them in separate holes, and do not route either against refrigerant tubing or moving parts.
- Use separate knockouts for line voltage and communication wiring.
- Route the connecting cable with conduit through the conduit panel hole.
- Ground the shield only at the outdoor unit when using shielded cable.
Leak check and evacuation for start-up
Carrier · D5FUAA refrigerant piping start-up
Pressure test the piping with dry nitrogen. Never use air or oxygen-containing gases for leak testing. Evacuation can use the Triple Evacuation Method or the Deep Vacuum Method.
- Hold the system at 500 psig (max. 550 psi) for a minimum of 30 minutes using dry nitrogen.
- Evacuate by the Triple Evacuation Method or the Deep Vacuum Method as outlined in the manual.
- Confirm the system holds 500 microns for 1 hour.
- Confirm the line set diameter matches the evaporator connections.
- For conventional fan coils, confirm the line set matches the outdoor unit size.
- Measure the liquid line length, calculate the additional charge, and record the final charge amount.
Leak check with dry nitrogen
Carrier · D5FUHA piping
Pressure test the piping before evacuation. Use dry nitrogen only. Never use air or oxygen-containing gases for leak testing.
- Pressurize the system with dry nitrogen to 500 psig.
- Do not exceed 550 psi.
- Hold the pressure for at least 30 minutes.
- Record YES or NO on the start-up checklist.
Line set match and additional charge
Carrier · D5FUHA single zone piping
Check the line set size against the evaporator connections and, for conventional fan coils, against the outdoor unit size. Calculate the extra charge from the liquid line length.
- Confirm the line set diameter matches the evaporator connections.
- For conventional fan coils, confirm the line set matches the outdoor unit size.
- Measure the liquid line length and calculate the additional charge.
- Record the final charge amount on the checklist.
Line set sizing and charge
Carrier · D5FSAA / D5FLAA single zone ductless system
The line set must match the evaporator connections, and the added charge must be calculated and recorded.
- Confirm the line set diameter matches the evaporator connections.
- For conventional fan coils, confirm the line set matches the outdoor unit size.
- Measure the liquid pipe length and calculate the additional charge.
- Record the liquid size, length and charge on the checklist.
- Record the final charge amount.
Line voltage terminal block connection
Carrier · Indoor unit power supply
Terminal block wiring depends on the supply voltage.
- For 208V or 230V supply, connect L1 and L2.
- For 115V supply, connect L1 and L2, where L2 is used as neutral (N).
Lock in service mode changes
Carrier · D5FUHA outdoor unit and remote controller
After all SERVICE mode changes are made, the outdoor unit must be powered down to lock the new settings in.
- After the last service change, turn off power to the outdoor unit.
- Keep the outdoor unit off for 3 minutes.
- Restore power to the outdoor unit.
Nitrogen flow while brazing the line set
Carrier · DLFULA evaporator coil
Nitrogen must flow through the system while the line set is brazed.
- Flow nitrogen through the system during all line set brazing.
No airflow setting needed
Carrier · All sizes
The indoor unit uses a constant air volume ECM motor that adjusts to static pressure up to 0.80 in.wc. ESP. The supplied remotes do not need to set airflow.
- Leave airflow on automatic and do not set CFM from the remote.
- Confirm the static pressure is within 0.80 in.wc. ESP.
Paired outdoor unit liquid line
Carrier · DLFULA evaporator coil paired with 38MURA outdoor units
When paired with the 38MURA outdoor units, the liquid line is a true liquid line and does not need both lines insulated.
- With 38MURA outdoor units, insulate only the line that needs it.
Power supply and disconnect requirements
Carrier · D5FUHA outdoor and indoor units
Supply voltage must stay within 90 to 110 percent of rated voltage. Fixed wiring needs a disconnect with at least 3 mm contact separation on all poles. A surge suppressor at the outdoor disconnect is recommended.
- Check the supply voltage is within 90 to 110 percent of rated.
- Install a disconnect or breaker that opens all poles with at least 3 mm (1/8 in) contact separation.
- Install a surge suppressor at the outdoor disconnect if possible.
- Use an individual branch circuit. Do not share it with other equipment.
Power supply and residual current protection
Carrier · Electrical connection of indoor unit
Use a dedicated circuit and a properly rated breaker. Fixed wiring needs an all-pole disconnect with at least 3 mm contact clearance in all poles. Where leakage current may exceed 10 mA, the RCD must have a rated residual operating current not above 30 mA. Do not share the outlet and do not modify or extend the power cable.
- Install a dedicated circuit and breaker that are not under-rated or defective.
- Fit an all-pole disconnect with at least 3 mm clearance in every pole.
- Where leakage may exceed 10 mA, fit an RCD rated at 30 mA or less.
- Confirm the unit is properly grounded and the power cable is secure and undamaged.
Preparation: air outlet, clearances and return air
Carrier · Indoor air handler
Set-up checks before the unit is connected and closed up.
- Remove all accessories and packing from the air outlet before installation.
- Keep a minimum 1 in (25.4 mm) clearance on all sides of the unit.
- For vertical installs, connect the lower end of the air outlet to the L-shaped metal duct and fasten with screws.
- If return air is ducted, run the duct flush with the floor and set the unit over the opening; all return air must pass through the coil.
- Seal around wires, refrigerant pipes and condensate pipes where they enter the cabinet, and seal any gaps around drain lines with duct tape or flexible sealant so warm air cannot enter.
- Keep the return air intake away from heat sources and warm or cool air that could skew the sensed return air temperature.
- Outlet side pipe length: 1.5 m (5.9 ft) as shown in the page 16 figure.
Pressure test and evacuation of field piping
Carrier · Split system field refrigerant piping
Field piping must be pressure tested with inert gas and then vacuum tested before charging. Evacuation limits apply as listed.
- Pressure test the low side at its design pressure and the high side at its design pressure. If the sides cannot be isolated, test the whole system at the low side design pressure.
- Hold the test pressure for at least 1 hour with no drop on the gauge. Gauge resolution must not exceed 5% of test pressure.
- Evacuate the system to 500 microns or the lower level required by local code.
- Isolate the pump from the system. Pressure must not rise above 1500 microns within 10 minutes.
Pressure, vacuum and leak test limits for field piping
Carrier · Field piping on D5FUAAH split systems
Limits for testing field refrigerant piping on split systems.
- Pressure test field piping with inert gas. Hold the test pressure for at least 1 hour with no drop on the gauge. Gauge resolution must not exceed 5% of the test pressure.
- After evacuation, isolate the pump. Pressure must not rise above 1500 microns within 10 minutes. Vacuum must reach 500 microns or lower, or the level required by local code.
- Test field-made indoor joints at at least 125% of the maximum allowable pressure. Sensitivity must be 1/8 oz (5 g) per year or better. No leak is allowed.
Read the full manual before installation
Carrier · D5FULA crossover evaporator coil, sizes 24K - 60K
Read the whole instruction manual before starting the installation.
Refrigerant joints and piping
Carrier · D5FULA crossover evaporator coil with flammable refrigerant
Keep refrigerant pipe runs to a minimum and protect them from physical damage. Use brazed or welded joints on the indoor side, not detachable joints. Mechanical connections must be reachable for service. Seal open pipe ends during storage.
- Seal pipe openings by pinching or taping them to keep out oil, water and dirt.
- Make sure all field joints can be inspected before they are covered.
Refrigerant leak sensor orientation
Carrier · D5FUHA
The unit includes a refrigerant leak mitigation system (R-454B). The leak sensor does not need to be re-oriented for different install positions.
- Do not reorient the refrigerant leak sensor for the chosen install position.
Refrigerant leak sensor wiring and secondary input
Carrier · D5FULA with R454B leak mitigation kit
The leak sensor connects to the primary leak mitigation input at CN8 on the interface board. A secondary input at CN5 is available but must be enabled with DIP switch SW5.
- Connect the refrigerant sensor wire to CN8 (primary, active by default).
- To use the secondary input at CN5, turn on DIP switch SW5.
- Follow the wiring diagram and the leak mitigation kit label for operating details.
Refrigerant line routing and burial
Carrier · DLFULA evaporator coil with outdoor unit
Outdoor units ship with a full R410A charge. Charge, line sizing and capacities assume runs of 25 ft (7.6 m). Lines must not be buried in the ground. If burial is unavoidable, do not bury more than 36 in (914 mm), and give the service valves at least 6 in (152 mm) of vertical rise to prevent refrigerant migration.
- Keep line runs near 25 ft (7.6 m) or adjust charge and line sizing to suit.
- Do not bury lines in the ground.
- If burial cannot be avoided, keep burial depth to 36 in (914 mm) maximum.
- Provide at least 6 in (152 mm) vertical rise to the service valves.
Refrigerant pipe burial limits
Carrier · D5FUAA system piping
Do not bury more than 36 in (914 mm) of refrigerant pipe. If any pipe is buried, there must be a 6 in (152 mm) vertical rise to the outdoor unit valve connections. Too much buried pipe lets refrigerant migrate during shutdown and can slug the compressor at start-up.
- Keep buried refrigerant pipe to 36 in (914 mm) or less.
- If any pipe is buried, provide a 6 in (152 mm) vertical rise to the outdoor valve connections.
Refrigerant piping leak check
Carrier · D5FSAA / D5FLAA ductless air handler system
The system is pressure-tested before evacuation. Use dry nitrogen only.
- Pressurise the system to 500 psig, with a maximum of 550 psi.
- Hold the pressure for at least 30 minutes using dry nitrogen.
- Never use air or oxygen-containing gases for this test.
- Record YES or NO on the start-up checklist.
Remote ON/OFF input (CN2, JR1)
Carrier · D5FUAA indoor unit
Lets an external switch turn the unit on and off. The unit responds within 2 seconds of a change.
- Remove jumper JR1 to enable the ON/OFF function.
- Open the switch to turn the unit off. Close it to turn the unit on.
- With the switch open, the unit ignores the remote or wired controller and shows CP.
Remove J1 short connector for water level switch
Carrier · Indoor main board
The J1 short connector must be removed before the water level switch can be used.
- Remove the short connector on J1 when using the water level switch function.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.