Carrier Mini-Split: Pressure test and evacuation of field refrigerant piping
Pressure test and evacuation of field refrigerant piping on a Carrier mini-split: Field piping must be pressure tested with inert gas and vacuum tested before charging.
Applies to: Split systems, field-made piping
How to fix pressure test and evacuation of field refrigerant piping: step by step
- Pressure test the field piping with nitrogen to 500 psi.
- Remove the pressure source and hold the pressure for at least 1 hour. The gauge must show no drop; gauge resolution must not exceed 5% of test pressure.
- Evacuate the system. Once it reaches the required vacuum level, isolate the pump.
- Confirm the pressure does not rise above 1500 microns within 10 minutes.
- Use a vacuum of 500 microns or less, or the level required by local code if that is stricter.
- Test field joints indoors at 125% of maximum allowable pressure with sensitivity of 1/8 oz (5 g) per year; no leak allowed.
If the unit shows an error code, look it up: Carrier Mini-Split codes
Source: Carrier D5FSOAH installation manual, p. 5. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.