Carrier Mini-Split: Prepare refrigerant pipe ends (cut, deburr, flare)
Prepare refrigerant pipe ends (cut, deburr, flare) on a Carrier mini-split: Clean, square and properly flared ends are needed for an airtight joint. Only the specified refrigerant may go into the system.
Applies to: Copper refrigerant line sets 6K-18K
How to fix prepare refrigerant pipe ends (cut, deburr, flare): step by step
- Measure the distance between the indoor and outdoor units, then cut the pipe a little longer than that.
- Cut at a true 90° angle. Avoid oblique, rough or warped cuts, and do not dent or deform the pipe.
- Hold the pipe pointing down and remove all burrs with a reamer or deburring tool.
- Seal the pipe ends with PVC tape while preparing them to keep debris out.
- Sheath the pipe with insulation.
- Put the flare nuts on both ends facing the correct direction before flaring, because they cannot be turned after flaring.
- Remove the PVC tape just before flaring. Clamp the flare form so the pipe end extends beyond it.
- Place the flaring tool on the form and turn the handle clockwise until the flare is fully formed.
- Remove the tool and form, then check the flare for cracks and an even surface.
If the unit shows an error code, look it up: Carrier Mini-Split codes
Source: D5FSOAH installation instructions, p. 19. Written in our own words as a summary; always check the original manual.
General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.