NTI Boiler: Installation checklist sign-off (commissioning)

Updated · by Aurora Star Tech Inc.

Installation checklist sign-off (commissioning) on a NTI boiler: What I usually see at handover is a boiler that runs fine but nobody wrote anything down. This checklist is the sign-off that fixes that. It covers wiring, supply voltage, startup, the flame and combustion numbers, and the final approval signature. Do it on every TRX150 before you leave the job, because it is a lot cheaper than the callback. The common miss is skipping the combustion analyzer and trusting your eyes on the flame.

Homeowner with a boiler problem? Call (647) 657-2977 or book a service call — licensed technicians across Vaughan and the GTA.

Applies to: TRX150

Common causes of installation checklist sign-off (commissioning)

  • Wiring not matching the boiler wiring diagram, or polarity reversed
  • Supply voltage off from the 120 V AC on the rating plate
  • Custom site parameters set but never tested
  • Flame or combustion values not verified with an analyzer
  • Paperwork left unsigned

How to fix installation checklist sign-off (commissioning): step by step

  1. Confirm wiring follows the boiler wiring diagram, polarity is correct, and supply voltage matches the rating plate (120 V AC).
  2. Confirm the boiler has been started and the gas valve adjusted if needed.
  3. Confirm the installation has been set up for the site and all customized parameters have been tested.
  4. Confirm proper boiler operation through a full call for heat.
  5. Check the burner flame through the sight glass. Verify combustion values with a calibrated combustion analyzer.
  6. If the flame does not look normal, have a qualified service technician clean it. See the flame sight glass window.
  7. Leak-check gas joints one more time and look over the condensate line and vent connections.
  8. Sign and date the final installation approval.
Safety: Gas, electrical and refrigerant work must be done by a licensed technician. Turn off power and gas before servicing, never bypass a safety control, and always follow the manufacturer's manual for your exact model.

If the unit shows an error code, look it up: NTI Boiler codes

Models

TRX085TRX110CTRX150TRX199TRX199C

Source: NTI TRX150 manual, p. 82. Written in our own words as a summary; always check the original manual.

General guidance for qualified technicians. The manufacturer's installation and service manual and local codes always take priority. Aurora Star Tech is not affiliated with, endorsed by or sponsored by any equipment manufacturer; brand and model names are used only to identify equipment and belong to their owners.